A development consent in NSW generally lapses five years after the date it starts to operate, under section 4.53(1) of the Environmental Planning and Assessment Act 1979, unless the council sets a different period. It does not lapse if building, engineering or construction work relating to the approved development is physically commenced on the land before that date (section 4.53(4)). For consents granted on or after 15 May 2020, section 96 of the Environmental Planning and Assessment Regulation 2021 says survey pegs, soil test bore holes, acoustic testing, ancillary vegetation removal and ground marking do not count. For an investor holding an approved duplex or townhouse site, that means a consent is a wasting asset until real work starts, and “a few survey pegs” is no longer a safe way to keep it alive.
Key takeaways
- The default lapse period is 5 years from the date the consent operates, and the council can specify a different period in the consent.
- Once building, engineering or construction work has physically commenced, the consent does not lapse, but since 15 December 2025 councils can issue a complete works order where work has commenced but not been completed.
- For consents granted on or after 15 May 2020, section 96 of the EP&A Regulation 2021 excludes bore holes, soil or water testing, survey work and pegs, acoustic testing, ancillary vegetation removal and ground marking from counting as commencement.
- Consents granted before 15 May 2020 are still tested under the older, broader case law, which accepted some preparatory work.
- The work relied on must be lawful and must relate to the approved development, which in practice means a construction certificate (or subdivision works certificate) must be in place first.
Who this is for: property investors and developers holding an approved DA for a duplex, townhouses or a subdivision in Sydney or regional NSW, and buyers looking at a site sold “with DA approval”, who need to know whether the consent is still alive and how to keep it that way.
How long does a development consent last in NSW?
Section 4.53(1) of the EP&A Act sets the general rule: a consent lapses five years after the date from which it operates. The NSW Department of Planning’s homeowner guide to determinations puts it simply: the consent lasts 5 years unless the council specifies another period, and if physical commencement has occurred the consent does not lapse. The consent “operates” from the date in the notice of determination, or for a deferred commencement consent, from the date the deferred matters are satisfied. If the consent is modified or appealed, check the consent documents carefully, because the operative date is the one that counts, not the date of a later modification.
Councils occasionally specify a shorter period, particularly where there is a strategic reason (for example, an area being re-planned), and the Act allows that in limited circumstances. Read the first page of the consent and the general conditions. If a lapse period other than five years is stated, it applies.
What counts as physical commencement since 2020?
Section 4.53(4) says a consent for the erection of a building, the subdivision of land or the carrying out of a work does not lapse if building, engineering or construction work relating to it is physically commenced on the land before the lapse date. For many years the courts read that broadly. The Law Society of NSW’s 2024 submission to the Legislative Assembly inquiry into historical consents summarises the case law: survey work with pegs, site clearing and geotechnical work were accepted as physical commencement.
That changed on 15 May 2020. The Environmental Planning and Assessment Amendment (Lapsing of Consent) Regulation 2020 introduced a stricter test, now section 96 of the EP&A Regulation 2021. Work is not taken to have been physically commenced merely by doing one or more of these things:
| Activity | Counts as commencement? (consents granted on or after 15 May 2020) |
|---|---|
| Creating a bore hole for soil testing | No |
| Removing water or soil for testing | No |
| Survey work, including placing pegs or survey equipment | No |
| Acoustic testing | No |
| Removing vegetation as an ancillary activity | No |
| Marking the ground to show how the land will be developed | No |
| Excavation for footings, laying a slab, installing approved stormwater or sewer works, demolition that is part of the approved works | Generally yes, if lawful and related to the consent (a question of fact in each case) |
The word “merely” matters. The listed activities do not count on their own. Substantive construction work related to the approved development is what saves the consent. Section 96 does not apply to consents granted before 15 May 2020, so an older consent is still assessed under the broader case law, a point the Law Society’s submission makes directly.
Commencing is no longer the end of the story. The Planning System Reforms Act 2025 amended sections 9.34 and 9.35 and Schedule 5 of the EP&A Act, from 15 December 2025, so that a complete works order can be issued where works under a consent have commenced but not been completed. The same amendments allow the Planning Secretary to modify or revoke very old consents (the Regulation limits this to consents granted more than 25 years ago). A token start followed by years of inactivity now carries more risk than it used to.
What makes commencement work valid?
Two practical requirements trip people up. First, the work must be lawful. Building work under a development consent generally needs a construction certificate before it starts, and subdivision works need a subdivision works certificate, as the NSW Planning Portal’s post-consent certificates page explains. Work carried out without the required certificate, or in breach of a condition that had to be satisfied before work started, risks being disregarded. Second, the work must relate to the approved development, not to something else on the site.
In practice, before relying on commencement:
- Confirm the consent’s operative date and lapse date, including any specified period.
- Check which conditions must be satisfied “prior to the issue of a construction certificate” and “prior to the commencement of works”, and satisfy them.
- Obtain the construction certificate (or subdivision works certificate) and appoint a principal certifier.
- Give the notice of commencement required by the consent and the Regulation.
- Carry out substantive work that clearly forms part of the approved development, such as footing excavation and pouring, or approved civil works.
- Document it: dated photographs, the certifier’s inspection record, survey of set-out, invoices.
- Keep the records with the title documents. A future buyer or lender will ask.
Buying a site “with DA approval”? What to check
For investors, an approved DA can add value, but only if it is alive and buildable. The checks we run on a site sold with an approval:
- Lapse date. Work it out from the notice of determination and any specified period. A consent with eight months left is worth far less than one with four years.
- Pre-2020 or post-2020. The commencement test depends on the grant date.
- Commencement claims. If the vendor says works have commenced, ask for the construction certificate, the commencement notice and the evidence. Pegs on a post-2020 consent are not enough.
- Conditions. Some conditions (contributions, Sydney Water requirements, bonds) cost real money before any building work, and must be costed into the purchase.
- Controls that have changed. If the consent lapses, a new DA is assessed against current controls. Where the Low and Mid-Rise Housing reforms or a new LEP now allow more, a lapse may matter less. Where controls have tightened, the old consent may be the only route to that yield.
The common mistake is relying on a lapse date in the agent’s brochure. Read the consent.
Can a consent be extended?
Not in the way many people assume. The temporary COVID-era extended lapse provisions were removed from section 4.53 on 15 December 2025, although consents that already had extended lapse dates keep them. There is no general application to “extend” a five-year consent before it lapses. The Act has allowed extensions in particular cases, and temporary COVID-era measures added time to some consents, but for a typical residential consent granted today the practical options are to commence before the lapse date or to lodge a new DA. A section 4.55 modification does not reset the lapse date. If you can see that you will not be ready to build in time, start the construction certificate process early enough to carry out genuine work, or plan for a fresh DA.
Definitions
- Lapse
- The point at which a development consent stops having effect because the approved development was not physically commenced within the lapse period.
- Physical commencement
- Building, engineering or construction work relating to the approved development, physically carried out on the land before the lapse date, under section 4.53(4) of the EP&A Act.
- Operative date
- The date a consent starts to operate, usually the date in the notice of determination, from which the lapse period is counted.
- Construction certificate
- The certificate confirming the detailed building plans comply with the Building Code of Australia and the consent, required before building work under a DA starts.
- Section 96 test
- The rule in the EP&A Regulation 2021 that listed preparatory activities do not, on their own, count as physical commencement for consents granted on or after 15 May 2020.
Frequently asked questions
How long is a DA valid in NSW?
Generally 5 years from the date the consent operates, unless the council specified another period. Once work has physically commenced, the consent does not lapse.
Do survey pegs stop a DA from lapsing?
Not for consents granted on or after 15 May 2020. Section 96 of the EP&A Regulation 2021 says survey work, including placing pegs, does not by itself count as physical commencement. Older consents are assessed under earlier case law.
Is there a time limit to finish building once work starts?
Section 4.53 sets no completion deadline once work has physically commenced. However, amendments in force since 15 December 2025 allow a development control order requiring works to be completed to be issued where works have commenced but not been completed.
Does a modification reset the 5 year lapse date?
No. A section 4.55 modification changes the approved development, but the lapse period still runs from the original consent’s operative date.
We check lapse dates, commencement evidence and conditions as part of every development due diligence report on approved sites, and where a consent is close to lapsing we advise whether to commence, modify or lodge fresh, including a new dual occupancy DA under current controls. If you hold or are buying an approved site, request a fee proposal for a consent review.
Sources and references
- Environmental Planning and Assessment Act 1979, section 4.53 Lapsing of consent, accessed October 2026
- Environmental Planning and Assessment Regulation 2021, section 96 Physical commencement, accessed October 2026
- Law Society of NSW, submission to the Inquiry into historical development consents in NSW (14 June 2024), accessed October 2026
- NSW Department of Planning, Your guide to the DA process, Stage 4 Determination, accessed October 2026
- NSW Planning Portal, Post-consent certificates, accessed October 2026
- NSW Department of Planning, Housing and Infrastructure, Information sheet: First commencement of the Planning System Reforms Act 2025 (complete works orders, historical consents, section 4.53), accessed October 2026
Information disclaimer. This article is general planning information prepared by the URBA Planning Team and is current at the date of publication. It is not planning, legal or financial advice for any specific property. Planning instruments, development control plans, state policies and the National Construction Code are amended regularly and councils interpret them differently; the controls quoted here should be confirmed against the versions in force at the date of lodgement and against the consent authority’s current requirements. Reliance on this article is at the reader’s own risk. URBA Planning, a division of Contrive Consultants Pty Ltd, accepts no liability for loss arising from its use. For advice on a specific site, contact URBA for a fee proposal.