In NSW, a development application is “deemed refused” once the assessment period set by the Environmental Planning and Assessment Regulation 2021 has passed without a decision: 40 days for ordinary development and 60 days for designated or integrated development, under section 8.11 of the Environmental Planning and Assessment Act 1979. Deemed refusal is not a real refusal. Nothing is recorded against the site, and the council usually keeps assessing. What it does is give the applicant the right to appeal to the Land and Environment Court as if the DA had been refused. Since 21 March 2026 that right lasts until the application is actually determined, rather than expiring 6 months after the deemed refusal date. For most house, duplex and townhouse DAs in Sydney, the better move is to find out why the DA is stalled and fix that, and keep the appeal in reserve.
Key takeaways
- The deemed refusal period is 40 days for ordinary development, 60 days for designated or integrated development and 90 days for State significant development.
- The assessment clock stops while the council is waiting on information it has asked for, so a DA lodged three months ago may have used far fewer than 40 assessment days.
- A deemed refusal gives the applicant the same right to appeal under section 8.7 as an actual refusal, and since 21 March 2026 that right continues up until the DA or modification is determined, even where an earlier deemed refusal appeal period had expired.
- Appealing a deemed refusal moves the decision to the court, which is expensive and ends the informal negotiation with the council officer.
- Most stalled residential DAs are stalled for a reason that can be found and fixed: an outstanding referral, an unanswered request for information or unresolved objections.
Who this is for: developers, builders and owners with a dual occupancy, townhouse or new house DA that has sat with a Sydney or regional NSW council for months, who need to decide whether to push the council, wait or appeal.
What does “deemed refusal” actually mean?
Section 8.11 of the EP&A Act, read with the Regulation, says that if a consent authority has not determined a development application within the deemed refusal period, the applicant may treat the application as refused for the purpose of an appeal. The Land and Environment Court’s guidance on development application appeals summarises the periods:
| Type of development | Deemed refusal period |
|---|---|
| Ordinary local development (most houses, dual occupancies, townhouses, small subdivisions) | 40 days |
| Designated development or integrated development (for example, a DA needing a bushfire safety authority or a water approval) | 60 days |
| State significant development | 90 days |
| Modification application under section 4.55 or 4.56 | Generally 40 days after the application was made |
The point many applicants miss is that deemed refusal is a right, not an outcome. The council does not issue a notice. The DA stays open on the NSW Planning Portal. In practice councils keep assessing DAs that have passed the deemed refusal date, and most are determined in the ordinary way.
Why does a DA lodged months ago still count as under 40 days?
Because the assessment clock is not a calendar. The NSW Department of Planning’s homeowner guide to lodging a DA explains that if the council needs more information, the assessment clock stops until you provide it. Under the Regulation the clock also pauses in other circumstances, and it does not run before the application is formally accepted on the Planning Portal.
A typical Western Sydney duplex DA might look like this: lodged on the Portal, accepted after an administrative check, notified to neighbours, then an RFI issued on day 25 asking for amended stormwater plans. If the engineer takes seven weeks to respond, those seven weeks are not assessment days. When the response goes in, the clock restarts at day 25. The DA has been with the council for three months, but it is not yet deemed refused.
The Planning Portal’s application tracker shows the status, and many councils show assessment days on their own DA trackers. Check both before you assume the council is simply sitting on the file.
Should you appeal a deemed refusal?
Sometimes, but rarely as a first move. The Land and Environment Court confirms that an applicant may appeal under section 8.7 when the application is taken to have been determined. Amendments made by the Planning System Reforms Act 2025, in force from 21 March 2026, extend that right up until the DA or modification application is determined, and the Department’s information sheet notes there are no transitional provisions, so applications whose earlier deemed refusal appeal rights had expired can now be appealed. For houses and dual occupancies the appeal runs under the residential process in section 34AA of the Land and Environment Court Act 1979: a conciliation conference with a commissioner, then an immediate decision if no agreement is reached.
An appeal can make sense when:
- the council has clearly signalled it will refuse, but has not yet taken the DA to a decision, and the clock is costing you holding costs;
- the DA has been fully assessed, every RFI answered, and it has stalled for months with no explanation;
- the issue between you and the council is a genuine merit disagreement that a commissioner should resolve.
An appeal is usually the wrong move when:
- an RFI is still outstanding, because the court will expect the same information;
- the DA is waiting on a referral to a state agency (Transport for NSW, the Rural Fire Service, Water NSW), which the court process will not speed up much;
- the assessing officer is engaged and working through issues with you. Filing an appeal ends that conversation and puts lawyers between you.
Once an appeal is filed, the council’s role changes from assessor to respondent. Costs rise on both sides, and the council will file a statement of facts and contentions that often lists more issues than the officer would have raised in an RFI.
How to unstick a slow DA before it gets to court
- Check the Portal status and the council tracker. Note the lodgement date, the acceptance date and any RFI dates.
- Read every RFI and referral response. A DA “waiting on applicant” is a different problem to one waiting on the council.
- Ask the assessing officer, in writing, for the outstanding issues and the expected determination pathway (delegated decision, local planning panel, or council meeting).
- Answer every issue in one coordinated package. Partial responses restart the same cycle.
- If objections are the hold-up, consider small design changes that answer the strongest objection directly.
- If the DA is going to a local planning panel, ask for the meeting date. Panel agendas fix the timetable.
- Only then weigh an appeal, with a planner’s honest view of the merit and a lawyer’s view of cost.
The mistakes that keep DAs stuck
The most common is a slow response to an RFI. Applicants wait for an architect, then an engineer, then a surveyor, and send the answers in three letters over two months. Councils then re-assess each piece separately. The second is answering the question that was not asked: a 40 page report in response to a one-line request for an amended landscape plan. The third is treating the deemed refusal date as a deadline the council has broken. It is not a breach, and an email saying so rarely helps.
The other quiet cause is lodgement quality. DAs lodged without the documents councils list in their DA checklists are slower to accept, more likely to attract an early RFI, and more likely to stall. A complete Statement of Environmental Effects that addresses every LEP and DCP control at lodgement is the cheapest way to avoid the question of deemed refusal altogether.
Definitions
- Deemed refusal
- The point at which an undetermined DA is treated as refused for appeal purposes, because the assessment period in the Regulation has passed without a decision.
- Assessment clock
- The count of assessment days under the EP&A Regulation 2021, which stops while the council is waiting on requested information.
- Request for information (RFI)
- A council’s written request for further plans, reports or clarification needed to complete its assessment.
- Integrated development
- Development that needs an approval from another state agency under a listed Act, such as a bushfire safety authority, so the DA is referred to that agency.
- Statement of facts and contentions
- The document a council files in a court appeal setting out the reasons it says the development should be refused.
Frequently asked questions
How long does a council have to decide a DA in NSW?
The deemed refusal period is 40 days for ordinary development and 60 days for designated or integrated development. That is not a deadline the council must meet, and the clock stops while the council waits for information, but after it passes you may appeal as if the DA had been refused.
Does deemed refusal mean my DA was rejected?
No. Nothing is issued and the DA stays open. It simply gives you a right of appeal. The council can and usually does keep assessing the application.
How long do I have to appeal a deemed refusal?
Since 21 March 2026, the right to appeal a deemed refusal continues until the application is determined. Once the council makes an actual decision, the ordinary appeal period for that decision applies instead.
Will appealing speed up my DA?
Not always. Residential appeals move to a conciliation conference relatively quickly, but you will need to fund planning and legal work, and the council may raise more issues in its contentions than it did in assessment.
We take over stalled DAs regularly: we read the file, identify what the council is actually waiting for, and prepare a single complete response through our RFI response service. On new projects, a thorough Statement of Environmental Effects at lodgement is the best protection against delay. If your DA in Blacktown, Penrith, Liverpool or anywhere else in NSW has gone quiet, request a fee proposal for a file review.
Sources and references
- Environmental Planning and Assessment Act 1979, Division 8.3 Appeals (sections 8.7, 8.10 and 8.11), accessed October 2026
- NSW Department of Planning, Housing and Infrastructure, Information sheet: Second commencement of the Planning System Reforms Act 2025 (deemed refusal appeals from 21 March 2026), accessed October 2026
- Environmental Planning and Assessment Regulation 2021 (deemed refusal periods and assessment clock), accessed October 2026
- Land and Environment Court of NSW, Development application appeals, accessed October 2026
- Land and Environment Court of NSW, Residential development appeals, accessed October 2026
- NSW Department of Planning, Your guide to the DA process, Stage 2 Lodging your development application, accessed October 2026
Information disclaimer. This article is general planning information prepared by the URBA Planning Team and is current at the date of publication. It is not planning, legal or financial advice for any specific property. Planning instruments, development control plans, state policies and the National Construction Code are amended regularly and councils interpret them differently; the controls quoted here should be confirmed against the versions in force at the date of lodgement and against the consent authority’s current requirements. Reliance on this article is at the reader’s own risk. URBA Planning, a division of Contrive Consultants Pty Ltd, accepts no liability for loss arising from its use. For advice on a specific site, contact URBA for a fee proposal.