Demolition and asbestos in NSW: approvals, licences and what councils expect

Demolishing a house in NSW? When demolition is exempt, CDC or DA, the 10 square metre asbestos rule, licensed removal and how councils condition it.

Demolishing a house in NSW needs approval, either as part of a development application, as complying development under the Demolition Code of the Codes SEPP, or, for minor structures only, as exempt development. Exempt demolition must still be carried out in accordance with Australian Standard AS 2601-2001 and the work health and safety laws. The bigger issue for most owner builders is asbestos. Any home built before the mid-1980s is highly likely to contain asbestos products, and the total Australian ban did not take effect until December 2003. A home owner can remove up to 10 square metres of non-friable (bonded) asbestos in good condition. Anything more needs a licensed removalist, and friable asbestos must always be removed by a licensed specialist. Councils condition demolition tightly, and they notice when the asbestos steps are skipped.

Key takeaways

  • Demolition of a dwelling is usually approved with the new house DA or CDC, or separately as complying development under the Demolition Code; exempt demolition is only for minor structures.
  • Exempt demolition must comply with AS 2601-2001 (The demolition of structures) and work health and safety laws, and is not available on State heritage listed land or land under an interim heritage order.
  • Before the mid-1980s it is highly likely a home contains asbestos, and between the mid-1980s and 1990 it is likely; only accredited laboratory testing confirms it.
  • A SafeWork NSW Class B licence is needed to remove more than 10 square metres of non-friable asbestos; friable asbestos needs a Class A licensed removalist.
  • Asbestos waste must go to a licensed waste facility; it cannot go in household bins, council clean-ups or mixed skips.

Who this is for: owner builders and home owners planning a knock-down rebuild, a garage demolition or a major renovation of an older house in Western Sydney, the Central Coast or regional NSW, who need to get the approvals and asbestos steps right before the excavator arrives.

Does demolishing a house need council approval?

Yes. A house cannot be demolished as exempt development. The NSW Planning Portal lists three pathways for demolition generally:

Pathway When it is used Who approves
Exempt development (Codes SEPP Part 2, Subdivision 13) Minor structures only; must comply with AS 2601-2001 and WHS laws No approval, but standards must be met
Complying development (the Demolition Code) Demolition of a dwelling and outbuildings on land where complying development applies Council or a registered certifier, through a CDC
Development application Demolition with a new house or duplex DA, or where complying development is unavailable (for example, heritage) Council

For knock-down rebuilds, the most common approach is to include demolition in the new house approval, whether that is a DA or a CDC under the Housing Code. That keeps the conditions, the waste plan and the timing in one place. Separate demolition first, then a new house later, is common when the owner wants to sell a vacant lot or the house is unsafe, but it creates two approvals and two sets of conditions.

Exempt demolition cannot be carried out on land with an item on the State Heritage Register or land subject to an interim heritage order, unless a section 57 exemption under the Heritage Act 1977 applies. In a heritage conservation area or on a local heritage item, demolition of the main building needs a DA under clause 5.10 of the LEP, and is assessed on heritage merit.

How do you know if a house contains asbestos?

Cumberland City Council’s guidance is a good summary: if the home was built before the mid-1980s, it is highly likely to contain asbestos products; if built between the mid-1980s and 1990, it is likely; and because the total ban only took effect in December 2003, there is always a chance asbestos was used. The only certain way to know is testing by an accredited laboratory. Cumberland is explicit that demolishing a house or garage requires asbestos testing by a licensed contractor.

Common locations in older Sydney houses: fibro sheeting on external walls and eaves, wet area linings, vinyl floor tiles and their backing, roof sheeting on garages and sheds, fencing, and lagging around old hot water systems. A pre-demolition hazardous materials survey records where it is and how much there is, and that report drives the removal method and cost.

What can a home owner remove, and when is a licence needed?

The rules turn on the type and quantity of asbestos:

  • Up to 10 square metres of non-friable asbestos in good condition. A home owner can remove it without a licence and without council approval for minor renovation work, using the precautions in SafeWork and council guidance. Councils describe this as an allowance for minor work only.
  • More than 10 square metres of non-friable asbestos. SafeWork NSW requires a Class B asbestos removal licence before removing more than 10 square metres of non-friable asbestos or asbestos-containing material, or the asbestos-contaminated dust from that work.
  • Any friable asbestos. A Class B licence holder can only remove non-friable asbestos. Friable asbestos (crumbly, damaged or loose material such as old pipe lagging) must be removed by a Class A licensed removalist.

A whole house will almost always exceed 10 square metres, so demolition of a fibro or part-fibro house means a licensed removalist. Licensed removalists must notify SafeWork NSW of licensed removal work. After removal, a clearance inspection is usually required before demolition of the remaining structure proceeds, and councils and certifiers commonly ask for the clearance certificate.

What will the council’s demolition conditions require?

Demolition conditions vary by council, but the ones that appear on most residential consents and CDCs include:

  1. Compliance with AS 2601-2001 and the work health and safety laws.
  2. A hazardous materials or asbestos survey before work starts, and removal of asbestos by an appropriately licensed contractor.
  3. Notice to adjoining owners and the council before demolition begins, and site signage with the contractor’s details.
  4. Disconnection of services (electricity, gas, water and sewer) by the relevant authority or licensed trades before demolition.
  5. Erosion and sediment controls, dust suppression and protection of the footpath and street trees.
  6. A waste management plan, with receipts showing asbestos went to a licensed waste facility and other material was recycled or disposed of lawfully.
  7. Limited hours of work, set in the consent.

Keep every receipt and certificate. Certifiers often ask for asbestos disposal dockets and the clearance certificate before they will sign off the next stage, and a buyer’s solicitor may ask for them years later.

Where demolitions go wrong

The first problem is demolishing before the approval is issued, which is unauthorised work and can lead to penalty notices or a stop work order. The second is breaking asbestos sheeting with the excavator because the survey was skipped. That contaminates the soil and turns a simple demolition into a remediation job, sometimes with a contamination report needed before the new house DA can be determined. The third is asbestos in the skip. Cumberland’s guidance says asbestos must never be mixed with other waste, must go to a licensed facility and cannot go in household bins or council clean-ups. Fines for illegal disposal are significant.

Definitions

AS 2601-2001
The Australian Standard for the demolition of structures, required for exempt demolition and commonly referenced in consent conditions.
Non-friable asbestos
Asbestos bonded into another material, such as fibro sheeting, which is relatively stable when in good condition.
Friable asbestos
Asbestos that can be crumbled or reduced to powder by hand pressure when dry, which is high risk and needs a Class A licensed removalist.
Clearance certificate
A certificate from a licensed assessor or competent person confirming the area is safe after asbestos removal.
Demolition Code
The part of the Codes SEPP that allows demolition to be approved as complying development where the standards are met.

Frequently asked questions

Do I need approval to demolish a house in NSW?

Yes. Demolition of a house needs a DA or a complying development certificate. Exempt demolition only covers minor structures and must still comply with AS 2601-2001.

Can I remove asbestos myself in NSW?

Only up to 10 square metres of non-friable asbestos in good condition, as minor work. More than that needs a Class B licensed removalist, and any friable asbestos needs a Class A licensed removalist.

Is my 1970s house likely to contain asbestos?

Yes. Council guidance is that homes built before the mid-1980s are highly likely to contain asbestos products. Accredited testing is the only way to confirm it.

Where can I dispose of asbestos?

Only at a licensed waste facility. It cannot go in household bins, council clean-up collections or a skip with other waste. Some councils, such as Cumberland, run small-scale collection services.

On knock-down rebuilds we include demolition in the new house approval wherever that is the faster path, and our Statements of Environmental Effects address demolition, waste and asbestos so the council has what it needs at lodgement. For advice on whether to go DA or CDC, see our pathway advice, or request a fee proposal for your rebuild.

Information disclaimer. This article is general planning information prepared by the URBA Planning Team and is current at the date of publication. It is not planning, legal or financial advice for any specific property. Planning instruments, development control plans, state policies and the National Construction Code are amended regularly and councils interpret them differently; the controls quoted here should be confirmed against the versions in force at the date of lodgement and against the consent authority’s current requirements. Reliance on this article is at the reader’s own risk. URBA Planning, a division of Contrive Consultants Pty Ltd, accepts no liability for loss arising from its use. For advice on a specific site, contact URBA for a fee proposal.